General Manager

A team has 40 hours available for the next delivery window. The agreed work needs 32 hours of implementation and four hours of testing. Then a stakeholder asks for a dashboard export that adds eight hours. Calling the request small does not make the arithmetic fit.
I would ask the project lead to put the choices in front of the person who can approve a change to the baseline. The example below is a fictional internal software project. The estimates, authority and quality conditions belong to the exercise.
The approved release contains a request form and a supervisor view. Its acceptance conditions include the four hours of planned testing. There are 40 usable hours in the window and no approved extra capacity. The project lead may organise the agreed work. The sponsor must approve a change in scope or delivery date.
The requested export has a stated business purpose. A supervisor wants to prepare a weekly report without retyping the entries. Ask the requester which fields are needed, how often the report is used and whether an existing approved view can meet the immediate need. This clarification is part of evaluating the request. It does not itself change the release agreement.
| Work | Hours |
|---|---|
| Approved implementation | 32 |
| Approved testing | 4 |
| Current total | 36 |
| New export, including its implementation and checks | 8 |
| Total if added | 44 |
| Usable capacity | 40 |
The gap is four hours under the exercise assumptions. That is a capacity calculation. A feasible sequence also depends on who can do the work and when inputs, reviews and environments become available. Record those assumptions beside the estimate rather than treating spare hours as interchangeable.
Defer the export. Keep the agreed release and assess a later slot. State how the supervisor will produce the report in the meantime and whether that is acceptable to the process owner.
Exchange scope. The packet identifies an optional four-hour report-polishing task within the 32 hours. Removing it would give 32 total baseline hours, including the original four testing hours. Adding the eight-hour export would then use 40 hours. This option needs the sponsor’s agreement, the affected owner’s input and confirmation that removing the task does not invalidate the intended outcome.
Change capacity or timing. Assess whether four additional effective hours can be supplied or the date can move. A person becoming available is not automatically four usable hours after coordination and onboarding. Recheck the task sequence and acceptance criteria before offering that option as feasible.
For this exercise, testing remains an agreed acceptance condition in every option. The learner must name a supported recommendation, its assumptions and who must decide. They should communicate the request as pending until the authorised decision is recorded.
A short change record can hold the original baseline, the reason for the request, the evaluated alternatives, the forecast impact, the recommendation, the decision owner and the status. After approval, update the relevant plan and acceptance record and tell the people whose work changes. Record a rejected or deferred request too so it does not quietly reappear as assumed work.
The Association for Project Management describes change control as evaluating requests against the approved baseline and reaching an authorised decision. Its guidance supports considering the impact and updating the plan after approval. The worked hours and options here are original and do not establish a universal approval threshold.
Give one participant the project lead role and another the supervisor role. Ask the lead to explain the alternatives without hiding the constraint or dismissing the business need. Then change the packet so the optional four-hour task is essential for the release. The previous exchange is no longer available. Observe whether the lead revises the recommendation and communicates a new decision request.
In Arabic and English, keep the 40-hour capacity, 36-hour baseline, eight-hour change and approval rules equivalent. Record what the participant actually considered and any help provided. A useful replay shows how they adapt to changed evidence. A live project still needs its own authorised estimates and controls.
For an Altaius systems integration discussion, bring the current release boundary, the new business need and the decision owner. Those details make a scope conversation concrete before anyone promises an extra feature.
Association for Project Management, What is change control?, read 15 November 2026.